During a working session with Permanent Deputy Prime Minister Pham Gia Tuc on the morning of November 25, the Airports Corporation of Vietnam (ACV) reported that Component Project 3—covering essential airport facilities—has reached 88.6% of construction volume and disbursed 57% of its contract value.
However, the state airport operator assessed that completing all of Component Project 3 this year under the original contract schedule is impossible. Major packages—including the passenger terminal, Cargo Terminal No. 1, parking garage, and airport management system—are now projected to finish construction or trial runs only by June 2027.
ACV outlined three primary groups of bottlenecks holding back the project. First, certain materials and equipment changed manufacturers, brands, specifications, and origins compared to original contract terms. Contractors ordered, supplied, and installed these items before the investor approved the changes and before parties signed contract addenda.
Second, workers built and inspected several items according to approved construction drawings that did not match the approved technical design, while corresponding technical designs remain unadjusted.
Third, contractors executed certain components before obtaining formal approval for construction drawing dossiers.
According to the project investor, resolving these discrepancies is a mandatory prerequisite for final acceptance and licensing the airport for commercial operations. Based on actual progress across Component Projects 3 and 4, ACV proposed that the Government task the Ministry of Construction with conducting an overall schedule review and reporting to competent authorities to adjust Phase 1 completion to 2027–2028.
At the meeting, Deputy Minister of Construction Pham Minh Ha urged ACV to review each modification item by item to establish a legal basis for resolution. For materials and equipment altered from contract terms, authorities must evaluate not only quality and technical compliance, but also pricing and cost value, with quality inspection falling squarely under the investor’s responsibility.
Deputy Minister of Justice Nguyen Thanh Tu requested that ACV pinpoint a clear, definitive completion date to complete reporting procedures for competent authorities.
Meanwhile, Nguyen Cong Long, General Director of the Vietnam Air Traffic Management Corporation (VATM), noted that remaining tasks under Component Project 2 depend directly on infrastructure completion in Component Project 3. He urged prioritizing technical facilities and infrastructure hookups to ensure synchronized deployment of air traffic control systems.
Government Orders Progress Report Before December 10
Permanent Deputy Prime Minister Pham Gia Tuc instructed ACV to audit all remaining workloads under Component Project 3, clearly defining milestones for construction completion, equipment installation, trial runs, test operations, and commercial launch.
Because the project cannot finish in 2026 as originally approved by the National Assembly, ACV must submit a formal report to the Government and the Ministry of Construction within one week of November 25. Before December 10, the Ministry of Construction must report project progress to the Government for submission to competent authorities to consider adjusting the investment policy.
The Permanent Deputy Prime Minister ordered ACV to require contractors to mobilize maximum manpower, machinery, equipment, and financial resources—working overtime and extra shifts to accelerate construction and disbursement. “Strictly penalize or report to competent authorities any contractors failing to honor contract terms,” he said, emphasizing that user safety and convenience stand as top priorities for an international gateway. The airport may enter commercial operation only once all safety conditions are fully satisfied.
ACV must also establish a clear launch announcement timeline and notify airlines promptly following official approval so carriers can prepare resources, build operational plans, and arrange flight schedules.
Long Thanh Airport’s launch date has already undergone multiple revisions. In July, the Civil Aviation Authority of Vietnam projected official commercial operations starting December 1, 2026. By late October, ACV announced a launch target of midnight on December 24, capping initial operations at roughly 366 flights per week.
On November 5, Permanent Deputy Prime Minister Pham Gia Tuc tasked the Ministry of Construction and relevant agencies with reviewing conditions to bring the airport online before December 31, 2026. As recently as November 23, ACV still outlined a phased launch plan starting December 24 with gradually rising flight frequencies.
Spanning approximately 5,000 hectares with a total investment of nearly 16 billion USD, Long Thanh International Airport is being developed across three phases. Phase 1 includes two runways and one passenger terminal capable of handling 25 million passengers and 1.2 million tons of cargo annually. Phase 2 adds a third runway, a second passenger terminal, and auxiliary facilities, lifting total capacity to 50 million passengers and 1.5 million tons of cargo per year. Phase 3 completes all remaining components, scaling capacity to 100 million passengers and 5 million tons of cargo annually as Vietnam aims to establish a premier regional aviation transit hub.
Once operational, Long Thanh will operate alongside Tan Son Nhat International Airport as the dual aviation gateway for the Ho Chi Minh City metropolitan region, easing congestion at the existing airport and expanding international passenger and cargo capacity.
Source: vnexpress.net